英语翻译The Contractor shall be responsible for ensuring ,if necessary in co-operation with the appropriate other contractor,that all items of electrical and mechanical equipment are erected,maintained in good condition and commissioned under app

来源:学生作业帮助网 编辑:作业帮 时间:2024/04/28 06:46:56

英语翻译The Contractor shall be responsible for ensuring ,if necessary in co-operation with the appropriate other contractor,that all items of electrical and mechanical equipment are erected,maintained in good condition and commissioned under app
英语翻译
The Contractor shall be responsible for ensuring ,if necessary in co-operation with the appropriate other contractor,that all items of electrical and mechanical equipment are erected,maintained in good condition and commissioned under appropriate invironmental conditions which shall be approved by the Engineer.

英语翻译The Contractor shall be responsible for ensuring ,if necessary in co-operation with the appropriate other contractor,that all items of electrical and mechanical equipment are erected,maintained in good condition and commissioned under app
The Contractor shall be responsible for ensuring ,if necessary in co-operation with the appropriate other contractor,that all items of electrical and mechanical equipment are erected,maintained in good condition and commissioned under appropriate invironmental conditions which shall be approved by the Engineer.
合约(双方)者应该对安全保障负责,如果必要和其他的合适的合约者合作的情况下.所有的被安装的电子的和机械的设备的条款,应该被很好的维护,在合适的环境下投入使用.而且应该由工程师批准.

承包商将负责保证, 必须在与适当情况下合作其它承包商, 所有电子机械项目设备被架设, 被维护在好情况和被委任在将被工程师批准的适当的 情况下

如果有必要与适当的其他承包商合作,承包商本人应负责确保安装好了所有电气、机械设备,进行了例行保养,以及经工程师批准后适当条件下的试运行。

这应该是FIDIC合同里关于机械安装的条款
我的翻译是
承包商应确保所有安装好的电气和机械设备可以得到良好的维护,并在合适的环境中运行,如必须同其他合适的分包商共同合作时,需由(应该是*业主工程师*)工程师批准。
大概就这样吧
希望能帮到你...

全部展开

这应该是FIDIC合同里关于机械安装的条款
我的翻译是
承包商应确保所有安装好的电气和机械设备可以得到良好的维护,并在合适的环境中运行,如必须同其他合适的分包商共同合作时,需由(应该是*业主工程师*)工程师批准。
大概就这样吧
希望能帮到你

收起

what's the army contractor mean? 英语翻译The Contractor shall not be claim commission if and when the execution of the business concluded became impossible,whereas the impossibility is beyond JOP’s control.The Contractor has to refund payments to the CUSTOMER subsequently rega 英语翻译The Contractor shall be fully resonsible for the Plant,the Contractor's equipment and any other materials or equipment he intends to use for the carrying out of the Works. 英语翻译Owner / Owner’s Representative reserves the right to restrict the sue of Owner’s information to specific locations,by specified Contractor personnel,or under other such use restrictions and to require any Contractor key personnel or a 英语翻译The available capital is calculated by adding any financial sponsorships added to the net asset value of a contractor as indicated in the contractor’s financial statements,subject to the contribution make by financial sponsorships to av 英语翻译The performance security shall be reduced to ten percent (10%) of the value of the component covered by the extended defect liability to cover the Contractor’s extended defect liability in accordance with the provision in the PC,pursuan 英语翻译20% of the Contract Price equal to [USD 6,320.000] shall be paid to the Contractor on the date of Contract’s signature against a bank guarantee (advance payment bond) of the same value to be submitted by the Contractor to the Owner with 英语翻译To the extent that an underestimate or overestimate is caused by changes in the quantities of work,neither error will effect the contractor’s profit beyond the markup in the unit prices. 英语翻译For the down payments and payments of advance(s),the Contractor shall establish unconditional Bank Guarantees acceptable to the Owner from first class International bank operating in India and in favour of the Owner in the same amount whi 英语翻译Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the Engineer’s approval before the Start Date.All such insurance shall provide for compensation to be payable in the types and proportions 英语翻译shop drawing work is out of scope of thecontractor.however,if the fabrication drawings shownin appendix 8-4 as a sample are not sufficient for the contractor's fabricationwork,thecontractor shall consider the cost of further detail drawin 英语翻译These are the as-built surveys and they are used to check the contractor `s work and show locations of structures and their components ( water line ,sewer ,etc .) ,which will be needed for future maintenance ,changes ,and new construction 英语翻译是最后的一个从句.全句是:10% upon expiry of warranty period,however,redeemable after complete delivery and contractor's presentation of the bank guarantee in accordance with Annex 2 of the contract as far as not presented for 英语翻译China will provide accommodation and meals to CONTRACTOR's personnel while the personnel are on their '30 days on' work rotation at the field WORK SITES.请尽量保证翻译完整,有道,谷歌,百度翻译的可以走人, 英语翻译Dayworks are varied work inputs subject to payment on a time basis for the Contractor's employees and Equipment,in addition to payment for associated Materials and Plant 英语翻译RT最好把下面一段也翻译:Quality controls at sub-vendor plant will be witnessed by Contractor and by Vendor,following the same requirements and procedures defined for others inspections at vendor’s workshops and strictly followi 英语翻译Shipping is an area where great care needs to be taken.Exhibitions can avoid high shipping and drayage costs with assistance from operation managers.Encourage exhibitors to ship to the general contractor's warehouse in advance---especiall In the case of Contractor's complete adherence and without negligence to such loss or damage求译?